Yesterday we started the day by digging up a small section by the patio where the sidewalk will meet the Florida room. Then, while Rick ran to the store, I dug up the drain pipe that he buried a couple of days ago. During the night (doesn't that man every sleep?), he analyzed what he had done with the new drain, and he decided that running the pipe straight over from the box to the buried drain system would not work. He said that we had to excavate it so we could run some elbows down to lower the the pipe as it leaves the drain box. That really made sense since otherwise the drain pipe would be very near the bottom of the pavers. So off he went to buy elbows to angle the pipe down while I resurrected the recently buried drain pipe. Within a couple of hours, we had the drain pipe reconfigured and buried again.
The pile of paver base soon after it was delivered gave us plenty to do with it. |
Then we set our sights to getting the ground as level as possible in anticipation for the paver base, which was delivered by 7:00 this morning. The truck driver was wonderful. He drove half-way up the driveway and was able to carefully dump the paver base without getting hardly any on the grass. Sadly, we ordered 4.5 tons of paver base, and they delivered (and we paid for) 4.84 tons. We probably will have a little left over, so we will have to see how our efforts go tomorrow. Any left over base can be put down as a foundation for patio stones behind the shed.
Rick works on raking the side yard while I used the wagon to load, carry, and dump base for the sidewalk next to the patio. |
Moving 9,600 pounds of paver base is hard work! Thankfully, the weather was in the low 70s today, and we had a delightful breeze blowing. (In reality, we probably only move about 6,450 pounds today.) Working in the morning is no problem, but when the sun hits us in the afternoon, work grinds to a halt quickly.
The base before it is tamped down is a moist, loose mix of ground up stone and aggregate. |
We were able to get the entire area covered with the first layer by 10:30 this morning. Rick called the paver supply warehouse to see if they had a power tamper available. They did, so by noon we were home with one in the back of the truck. The man at the store told us that the tamper weighed about 60 pounds. Yeah, right. I have lifted 60 pound bags of concrete with Rick with no problem. This tamper I could not pick up!
The power tamper does a great job, but it is not something that I could begin to lift. |
What we finally did was to back up to the pile of paver base, slide the tamper off the truck, and let it fall into the mountain of paver base. From there, Rick could drag it down. So far, so good.
Compared to the first photo, you can see that we have reduced the size of the paver pile by more than half. |
The tamper works very well. By 1:15 this afternoon, our pile of paver base had shrunk considerably. We still have to add another layer tomorrow and to level things out, but hopefully by tomorrow at this time, we will almost be done with this step of the work. Then we are going to take a week off while Stephanie visits before we get a load of sand and start laying the pavers. Thank God Stephanie is coming. I need a break!